Fen Farm

Ecotricity, the first Green Electricity company in the world, approached BeBa to build a Solar Park in Lincolnshire. BeBa's unprecedented experience in the design, supply and construction of Solar Parks in Europe led to us being the first choice for this massive project, and we were the first UK EPC Contractor to be appointed to build a solar park. 

During the selection process, BeBa showed Ecotricity two of the 5MW solar parks in Germany, demonstrating that we would be able to meet their expectations for a state of the art Solar Park in the UK. 

BeBa's team of experts and engineers designed, managed, constructed and commissioned the new park, which consists of 60 rows of Sharp modules, totally nearly 900 kWp. The park is connected to an Emerson central inverter, which sits in inverter housing that BeBa designed. 

The Fen Farm solar park continues to out-perform expectations, and is monitored and maintained by BeBa to ensure this continues.  In the first 2 years, the site generated over one million kWh, saving around 544 tonnes of CO2 from being emitted into the atmosphere.  

Key Aims

  • Reduce C02 Emissions from Electricity Production  
  • Complement Wind Farm
  • Add to Energy Mix 

Fact File

Size of site:
899.47 kWp

Number of modules:
4862

Predicted AEP:
835,607kWh

Actual AEP:
868,759kWh

CO2 saving (yrs 1-2):
544 tonnes

 

Ecotricity

www.ecotricity.co.uk

Ecotricity were the world's first Green Electricity company, with a mission to change the way electricity is made and used in Britain. 

By using customers' electricity bills to fund the building of new sources of green energy, Ecotricity spend more each year per customer on new energy sources than any other energy company in the country.

Get in touch

Contact us today to speak with one of our professional team and find out how we can help you.

Newsletter signup